Application of the Last Planner System with Earned Value Management: A Case Study from a Road Construction Project in Peru
| International Journal of Civil Engineering |
| © 2026 by SSRG - IJCE Journal |
| Volume 13 Issue 1 |
| Year of Publication : 2026 |
| Authors : Erick Oswaldo Gamboa Tolentino, Iralmy Yipsy Platero Morejon, Noemi Parra Buelna |
How to Cite?
Erick Oswaldo Gamboa Tolentino, Iralmy Yipsy Platero Morejon, Noemi Parra Buelna, "Application of the Last Planner System with Earned Value Management: A Case Study from a Road Construction Project in Peru," SSRG International Journal of Civil Engineering, vol. 13, no. 1, pp. 63-75, 2026. Crossref, https://doi.org/10.14445/23488352/IJCE-V13I1P106
Abstract:
This paper examines whether a combined implementation of the Last Planner System (LPS) and Earned Value Management (EVM) improves productivity, schedule adherence, and cost control in a road project started with delays; the aim was to assess if the joint practice of collaborative planning and objective measurement could recover the project schedule, balance weekly production with the accelerated master schedule, and maintain financial efficiency. The methodology integrated pull planning, lookahead planning, and systematic constraint management to enhance the Percent Plan Complete (PPC) and the Constraint Coordination Index (CCI). In the meantime, key performance indicators such as Planned Value (PV), Earned Value (EV), Actual Cost (AC), and their derived metrics (Cost Variance CV, Schedule Variance SV, Cost Performance Index CPI, and Schedule Performance Index SPI) were monitored using the EVM procedure; this integrated measurement system provided advance warnings and guided prompt corrective actions on site; additionally, the results recorded a progressive maturation of plan reliability, expressed in the growing PPC value and the constant reduction of Reasons for Non-Compliance (RNC). Furthermore, schedule performance exceeded the planned values during the first three months and presented values below 1 in the last two months, explained by contractual deductions rather than actual delays. Cost efficiency was also confirmed by a final CPI of 1.03, a positive cost variance of S/ 43,421.06 as an effective saving, and an EV/PV ratio of 97.42%, consistent with the deducted project scope. It is concluded that the integration of LPS and EVM enabled the project to recover, align, and accelerate execution, offering a practical contribution by linking collaborative production control with earned value performance metrics.
Keywords:
Earned Value Management, Last Planner System, Road Project, Productivity, Resource savings.
References:
[1] ComexPerú, Infrastructure on Hold: 2,474 Projects Paralyzed as of December 2024, [Online]. Available: https://www.comexperu.org.pe/articulo/infraestructura-en-pausa-2474-obras-paralizadas-a-diciembre-de-2024
[2] Peruvian Institute of Economics (IPE), Cusco: The Region where Projects Do not Progress, Ipe.org.pe, 2024. [Online]. Available: https://ipe.org.pe/cusco-la-region-donde-las-obras-no-avanzan
[3] Herman Glenn Ballard, “The Last Planner System of Production Control,” Ph.D. Thesis, University of Birmingham, Birmingham, 2000.
[Google Scholar] [Publisher Link]
[4] Frank T. Anbari, “Earned Value Project Management Method and Extensions,” Project Management Journal, vol. 34, no. 4, pp. 12-23, 2003.
[CrossRef] [Google Scholar] [Publisher Link]
[5] Castañón Puga Manuel et al., “Earned Value Management Agent-Based Simulation Model,” Systems, vol. 11, no. 2, pp. 1-20, 2023.
[CrossRef] [Google Scholar] [Publisher Link]
[6] Yinmar Jhonatan Ramírez Abad, and Lucero Estefhany Caballero Chinchay, “Time and Cost Estimation for the Construction of Anchored Walls in Clay Soils: A Case Study of the Construction of the SAN Ignacio Hospital, Cajamarca Department,” Pakamuros Scientific Journal, vol. 11, no. 3, pp. 57-72, 2023.
[CrossRef] [Google Scholar] [Publisher Link]
[7] Max Joel Malpica Cabrera, Percy Junior Gil Lozano, and Manuel Urcia Cruz, “The Impact of Earned Value Management on a Social Construction Project,” YACHAQ, vol. 6, no. 1, pp. 71-84, 2023.
[CrossRef] [Google Scholar] [Publisher Link]
[8] Abdullah O. AlSehaimi, Patricia Tzortzopoulos Fazenda, and Lauri Koskela, “Improving Construction Management Practice with the Last Planner System: A Case Study,” Engineering, Construction and Architectural Management, vol. 21, no. 1, pp. 51-64, 2014.
[CrossRef] [Google Scholar] [Publisher Link]
[9] Ludwig Rivera, Hilario Baguec, and Chunho Yeom, “A Study on Causes of Delay in Road Construction Projects Across 25 Developing Countries,” Infrastructures, vol. 5, no. 10, pp. 1-16, 2020.
[CrossRef] [Google Scholar] [Publisher Link]
[10] Olli Seppänen, Glenn Ballard, and Sakari Pesonen, “The Combination of Last Planner System and Location-Based Management System,” Lean Construction Journal, pp. 43-54, 2010.
[Google Scholar] [Publisher Link]
[11] Daniel Pérez, Camilo Lagos, and Luis Fernando Alarcón, “Key Last Planner System Metrics to Assess Project Performance in High-Rise Building and Industrial Construction Projects,” Journal of Construction Engineering and Management, vol. 148, no. 01, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[12] R. William (Bill) Seed, Transforming Design and Construction: A Framework for Change, 1st ed., Virginia, USA: LCI, 2015.
[Google Scholar] [Publisher Link]
[13] Ministry of Economy and Finance, Supreme Decree No. 344-2018-EF, Government of Peru, 2018. [Online]. Available: https://www.gob.pe/institucion/mef/normas-legales/235964-344-2018-ef
[14] Glenn Ballard, and Iris Tommelein, “2020 Current Process Benchmark for the Last Planner® System of Project Planning and Control,” Lean Construction Journal, pp. 53-155, 2021.
[CrossRef] [Google Scholar] [Publisher Link]
[15] Ricardo Viana Vargas, Using Earned Value Management to Measure Project Performance, PMI, 2010. [Online]. Available: https://www.pmi.org/learning/library/earned-value-development-factor-compensation-tool-8427
[16] Glenn Ballard, and Gregory A. Howell, “An Update on Last Planner,” Proceedings 11th Annual Conference International Group for Lean Construction, pp. 1-10, 2003.
[Google Scholar]
[17] Lauri Koskela et al., The Foundations of Lean Construction, 1st ed., Design and Construction, pp. 134-149, 2002.
[Google Scholar] [Publisher Link]
[18] International Labour Organization, Safety and Health in Construction, 2021. [Online]. Available: https://www.ilo.org/es/resource/otro/seguridad-y-salud-en-la-construcci%C3%B3n-edici%C3%B3n-revisada
[19] Farook Hamzeh, Glenn Ballard, and Iris D. Tommelein, “Rethinking Lookahead Planning to Optimize Construction Workflow,” Lean Construction Journal, pp. 15-34, 2012.
[Google Scholar] [Publisher Link]
[20] S M Abdul Mannan Hussain, Seshadri Sekhar T, and B.S.R.K Prasad, “Implementation of Last Planner System for Improving the Construction Process,” International Journal of Engineering and Technology, vol. 9, no. 4, pp. 2835–2845, 2017.
[CrossRef] [Google Scholar] [Publisher Link]
[21] Sada Hasan, Zeynep Işık, and Gökhan Demirdöğen, “Evaluating the Contribution of Lean Construction to Achieving Sustainable Development Goals,” Sustainability, vol. 16, no. 8, pp. 1-24, 2024.
[CrossRef] [Google Scholar] [Publisher Link]
[22] V. Gonzalez, L.F. Alarcon, and F. Mundaca, “Investigating the Relationship between Planning Reliability and Project Performance,” Production Planning & Control, vol. 19, no. 5, pp. 461-474, 2008.
[CrossRef] [Google Scholar] [Publisher Link]
[23] Mayra Proaño-Narváez et al., “Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections,” Buildings, vol. 12, no. 3, pp. 1-17, 2022.
[CrossRef] [Google Scholar] [Publisher Link]
[24] Mark Novinsky et al., “Combined Application of Earned Value Management and Last Planner System in Construction Projects,” 26th Annual Conference of the International Group for Lean Construction, Chennai, India, pp. 775–785, 2018.
[CrossRef] [Google Scholar] [Publisher Link]
[25] Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 6th ed., Pennsylvania, USA: PMI, 2017.
[Google Scholar] [Publisher Link]
[26] Deng, Jie, and Wei Jian, “Estimating Construction Project Duration and Costs upon Completion Using Monte Carlo Simulations and Improved Earned Value Management,” Buildings, vol. 12, no. 12, pp.1-23, 2022.
[CrossRef] [Google Scholar] [Publisher Link]
[27] Ergo Pikas et al., “Digital Last Planner System Whiteboard for Enabling Remote Collaborative Design Process Planning and Control,” Sustainability, vol. 14, no. 19, pp. 1-27, 2022.
[CrossRef] [Google Scholar] [Publisher Link]
[28] Bayram Ateş, and Mohammad Azim Eirgash, “Proactive and Data-Driven Decision-Making using Earned Value Analysis in Infrastructure Projects,” Buildings, vol. 15, no. 14, pp. 1-16, 2025.
[CrossRef] [Google Scholar] [Publisher Link]

10.14445/23488352/IJCE-V13I1P106