Volume 13 | Issue 11 | Year 2026 | Article Id. IJCE-V13I11P111 | DOI : https://doi.org/10.14445/23488352/IJCE-V13I11P111An Integrated FMEA Action Priority and Dynamic RPN Model for Cost Overrun Risk Prioritization in Modular Construction: Evidence from Jakarta
Jannatul Ma’wa, Kartika Puspa Negara, Wisnumurti
| Received | Revised | Accepted | Published |
|---|---|---|---|
| 20 Jul 2026 | 04 Oct 2026 | 28 Oct 2026 | 27 Nov 2026 |
Citation :
Jannatul Ma’wa, Kartika Puspa Negara, Wisnumurti, "An Integrated FMEA Action Priority and Dynamic RPN Model for Cost Overrun Risk Prioritization in Modular Construction: Evidence from Jakarta," International Journal of Civil Engineering, vol. 13, no. 11, pp. 190-205, 2026. Crossref, https://doi.org/10.14445/23488352/IJCE-V13I11P111
Abstract
Modular construction promises productivity gains, shorter delivery times and improved sustainability, yet evidence on its cost performance is mixed: some studies report savings, whereas others report cost increases associated with design, manufacturing and logistics difficulties. Research on cost-overrun risk prioritization for modular construction in Indonesia remains limited, and the combined use of Action Priority (AP) and the Dynamic Risk Priority Number (Dynamic RPN) remains unexamined. This study proposes an integrated AP-based FMEA and Dynamic RPN framework in which AP determines the urgency of action and Dynamic RPN ranks risks within each AP level through an explicit integration rule. Data are obtained from 29 experienced practitioners in Jakarta through a questionnaire covering 34 risk factors in five lifecycle phases; 32 items are retained after validity screening. AP assigns all 32 risk factors to the Low level, whereas Dynamic RPN separates them into four classes (one Very High, seven High, sixteen Medium and eight Low) based on RPN share and percentile rank. Design or scope changes during module production rank first (6.39% of the total RPN), and the leading risk factor of every phase is classified as High or Very High, which indicates that cost-overrun risk spans the whole lifecycle. Because expert agreement is weak (Kendall's W = 0.083-0.144), the ranking is interpreted as a relative, perception-based ordering and not as a measure of realized cost overruns. The framework offers a transparent basis for differentiating cost-overrun risks when AP alone yields a uniform classification.
Keywords
Action Priority, Cost overrun, Dynamic risk priority number, Failure Mode and Effect Analysis with Action Priority, Modular construction.
References
- Mohammad Kamali, and Kasun Hewage, “Life Cycle Performance of Modular Buildings: A Critical Review,” Renewable and Sustainable Energy Reviews, vol. 62, pp. 1171-1183, 2016.
[CrossRef] [Google Scholar] [Publisher Link] - Hamza Pervez et al., “Evaluation of Critical Risk Factors in the Implementation of Modular Construction,” PLOS One, vol. 17, no. 8, pp. 1-27, 2022.
[CrossRef] [Google Scholar] [Publisher Link] - Ali Hassan Ali et al., “Modelling the Relationship between Modular Construction Adoption and Critical Success Factors for Residential Projects in Developing Countries,” International Journal of Construction Management, vol. 24, no. 12, pp. 1314-1325, 2024.
[CrossRef] [Google Scholar] [Publisher Link] - Chaesar Arung Samudera, Ir. Kartika Puspa Negara, and Ir. Eko Andi Suryo, “Analysis of Challenges in Implementing Modular Construction at PT X in Jakarta,” Civil Engineering Student Journal, vol. 1, no. 2, 2025.
[Publisher Link] - Oktaviani Turbaningsih, Ulfa Mutaharah, and Pramada Saputra, “The Study of Potential Application of Modular Construction in the Development of Indonesia?s New Capital City,” Journal of Civil Engineering, vol. 29, no. 3, pp. 207-216, 2022.
[CrossRef] [Google Scholar] [Publisher Link] - Arif Fajar Mudawarisman, Triwuryanto, and Sely Novita Sari, “Comparative Analysis of Conventional House Structure Costs with Risha in Magelang Regency,” EQUILIB, vol. 1, no. 2, 2020.
[Google Scholar] [Publisher Link] - Riza Fahlevi, Edison Hatoguan Manurung, and Agus Purba, “The Influence of Implementing Modular Construction Methods on Time and Cost Efficiency in Building Construction Projects,” International Journal of Multidisciplinary Research and Literature, vol. 4, no. 1, pp. 104-113, 2025.
[CrossRef] [Google Scholar] [Publisher Link] - Ibrahim Yahaya Wuni, and Geoffrey Qiping Shen, “Critical Success Factors for Modular Integrated Construction Projects: A Review,” Building Research & Information, vol. 48, no. 7, pp. 763-784, 2020.
[CrossRef] [Google Scholar] [Publisher Link] - Margaret P. Keorapetse, Helena Utzig, and Carlos T. Formoso, “Cost Control in Modular Construction: A Taxonomy for Effective Cost Management,” Proceedings of the 32nd Annual Conference of the International Group for Lean Construction (IGLC 32), Auckland, New Zealand, pp. 167-178, 2024.
[CrossRef] [Google Scholar] [Publisher Link] - Jae-Seung Lee, and Yea-Sang Kim, “Analysis of Cost-Increasing Risk Factors in Modular Construction in Korea using FMEA,” KSCE Journal of Civil Engineering, vol. 21, no. 6, pp. 1999-2010, 2017.
[CrossRef] [Google Scholar] [Publisher Link] - Ayaz Ahmad Khan et al., “Exploring Critical Risk Factors in Volumetric Modular Construction: Fault Tree Analysis with Stakeholders' Perspectives on Probability and Impact,” Journal of Architectural Engineering, vol. 29, no. 4, pp. 1-18, 2023.
[CrossRef] [Google Scholar] [Publisher Link] - Effects Analysis. FMEA Handbook, Michigan, AIAG & VDA. 2019.
[Google Scholar] [Publisher Link] - Filip Anackovski, Ivo Kuzmanov, and Roberto Pasic, “Action Priority in New FMEA as Factor for Resources Management in Risk Reduction,” International Journal of Scientific & Engineering Research, vol. 12, no. 4, pp. 921-925, 2021.
[Google Scholar] - Matthew Barsalou, “Investigation into a Potential Reduction of FMEA Efforts using Action Priority,” Management and Production Engineering Review, vol. 13, no. 4, pp. 59-71, 2022.
[CrossRef] [Google Scholar] [Publisher Link] - D.I. Panyukov et al., “FMEA Risk Analysis on the Basis of Action Priorities,” Russian Engineering Research, vol. 42, no. 10, pp. 1077-1080, 2022.
[CrossRef] [Google Scholar] [Publisher Link] - Mufide Narli, “A Dynamic Approach to FMEA-RPN Risk Classification: Comparing with the Classical FMEA Method,” Medycyna Pracy. Workers' Health and Safety, vol. 77, no. 2, pp. 89-99, 2026.
[CrossRef] [Google Scholar] [Publisher Link] - Argaw Gurmu et al., “Defects in Modular Building Construction: A Systematic Lifecycle Review and Implications for Sustainable Delivery,” Sustainability, vol. 18, no. 8, pp. 1-27, 2026.
[CrossRef] [Google Scholar] [Publisher Link] - Sherif Abdelmageed, and Tarek Zayed, “A Study of Literature in Modular Integrated Construction - Critical Review and Future Directions,” Journal of Cleaner Production, vol. 277, pp. 1-70, 2020.
[CrossRef] [Google Scholar] [Publisher Link] - Ayaz Ahmad Khan et al., “Volumetric Modular Construction Risks: A Comprehensive Review and Digital-Technology-Coupled Circular Mitigation Strategies,” Sustainability, vol. 15, no. 8, pp. 1-34, 2023.
[CrossRef] [Google Scholar] [Publisher Link] - Sabah Khodabocus, and Senem Seyis, “Trends and Future Directions of Risk Management Approaches Applied in Modular Construction Projects: Systematic Review and Meta-Analysis,” Uludag University Journal of the Faculty of Engineering, vol. 29, no. 1, pp. 311-330, 2024.
[CrossRef] [Google Scholar] [Publisher Link] - Enaam Ouda, and Mahmoud Haggag, “Cost-Benefit Analysis of Automating Modular Construction Manufacturing for Affordable Housing,” Frontiers in Built Environment, vol. 11, pp. 1-16, 2025.
[CrossRef] [Google Scholar] [Publisher Link] - Yanhui Sun et al., “Constraints Hindering the Development of High-Rise Modular Buildings,” Applied Sciences, vol. 10, no. 20, pp. 1-20, 2020.
[CrossRef] [Google Scholar] [Publisher Link] - Ibrahim Y. Wuni, Geoffrey Q.P. Shen, and Abba Tahir Mahmud, “Critical Risk Factors in the Application of Modular Integrated Construction: A Systematic Review,” International Journal of Construction Management, vol. 22, no. 2, pp. 133-147, 2022.
[CrossRef] [Google Scholar] [Publisher Link] - Seoyoung Jung, Seulki Lee, and Jungho Yu, “Identification and Prioritization of Critical Success Factors for Off-Site Construction using ISM And MICMAC Analysis,” Sustainability, vol. 13, no. 16, pp. 1-22, 2021.
[CrossRef] [Google Scholar] [Publisher Link] - E.M.A.C. Ekanayake et al., “Critical Supply Chain Vulnerabilities Affecting Supply Chain Resilience of Industrialized Construction in Hong Kong,” Engineering, Construction and Architectural Management, vol. 28, no. 10, pp. 3041-3059, 2021.
[CrossRef] [Google Scholar] [Publisher Link] - Xiaoyong Luo et al., “Research on the Modular Design Method and Application of Prefabricated Residential Buildings,” Buildings, vol. 14, no. 9, pp. 1-20, 2024.
[CrossRef] [Google Scholar] [Publisher Link] - Yasaman Shahtaheri et al., “Managing Risk in Modular Construction using Dimensional and Geometric Tolerance Strategies,” Automation in Construction, vol. 83, pp. 303-315, 2017.
[CrossRef] [Google Scholar] [Publisher Link] - Abdulkabir Opeyemi Bello et al., “Barriers to Modular Construction Systems Implementation in Developing Countries’ Architecture, Engineering and Construction Industry,” Engineering, Construction and Architectural Management, vol. 31, no. 8, pp. 3148-3164, 2024.
[CrossRef] [Google Scholar] [Publisher Link] - Naning Aranti Wessiani, and F Yoshio, “Failure Mode Effect Analysis and Fault Tree Analysis as a Combined Methodology in Risk Management,” IOP Conference Series: Materials Science and Engineering: International Conference on Industrial and Systems Engineering, Denpasar, Bali, Indonesia, vol. 337, pp. 1-12, 2018.
[CrossRef] [Google Scholar] [Publisher Link] - Lorenzo Ciani, Giulia Guidi, and Gabriele Patrizi, “A Critical Comparison of Alternative Risk Priority Numbers in Failure Modes, Effects, and Criticality Analysis,” IEEE Access, vol. 7, pp. 92398-92409, 2019.
[CrossRef] [Google Scholar] [Publisher Link] - Zhaojing Wang et al., “Precast Supply Chain Management in Off-Site Construction: A Critical Literature Review,” Journal of Cleaner Production, vol. 232, pp. 1204-1217, 2019.
[CrossRef] [Google Scholar] [Publisher Link] - Regulation of the Minister of Public Works and Public Housing Number 08/PRT/M/2016 of 2016 Concerning Instructions for the Implementation of Budget Accountability Verification at the Ministry of Public Works and Public Housing, Ministry of Public Works and Public Housing, 2016. [Online]. Available: https://peraturan.bpk.go.id/Details/104513/permen-pupr-no-08prtm2016-tahun-2016
- The Directorate General of Housing is Ready to Implement a Culture of Risk Awareness and Risk Management for Housing Programs, Ministry of Housing and Settlement Areas, 2024. [Online]. Available: https://pkp.go.id/berita/detail/ditjen-perumahan-siap-terapkan-budaya-sadar-risiko-dan-manajemen-risiko-untuk-program-perumahan
- Lin Liu et al., “Analyzing Cost Impacts across the Entire Process of Prefabricated Building Components from Design to Application,” Scientific Reports, vol. 15, no. 1, pp. 1-17, 2025.
[CrossRef] [Google Scholar] [Publisher Link] - A. S.T. Chang, J. S. Shih, and Y. S. Choo, “Reasons and Costs for Design Change during Production,” Journal of Engineering Design, vol. 22, no. 4, pp. 275-289, 2011.
[CrossRef] [Google Scholar] [Publisher Link] - Jeffrey Boon Hui Yap, and Martin Skitmore, “Investigating Design Changes in Malaysian Building Projects,” Architectural Engineering and Design Management, vol. 14, no. 3, pp. 218-238, 2018.
[CrossRef] [Google Scholar] [Publisher Link] - Mojtaba Valinejadshoubi, Ashutosh Bagchi, and Osama Moselhi, “Damage Detection for Prefabricated Building Modules during Transportation,” Automation in Construction, vol. 142, 2022.
[CrossRef] [Google Scholar] [Publisher Link] - Duy-Cuong Nguyen et al., “BIM-based Preassembly Analysis for Design for Manufacturing and Assembly of Prefabricated Bridges,” Automation in Construction, vol. 160, 2024.
[CrossRef] [Google Scholar] [Publisher Link] - Mughees Aslam, Edmund Baffoe-Twum, and Farhan Saleem, “Design Changes in Construction Projects – Causes and Impact on the Cost,” Civil Engineering Journal, vol. 5, no. 7, pp. 1647-1655, 2019.
[CrossRef] [Google Scholar] [Publisher Link]