A Hybrid FMEA and K-Means Clustering Approach for Risk Identification and Analysis on Road Infrastructure Project in Nepal


Roshan Adhikari, Sunil Thakur, Anjay Kumar Mishra

Received Revised Accepted Published
18 Aug 2026 13 Nov 2026 18 Nov 2026 27 Nov 2026

Citation :

Roshan Adhikari, Sunil Thakur, Anjay Kumar Mishra, "A Hybrid FMEA and K-Means Clustering Approach for Risk Identification and Analysis on Road Infrastructure Project in Nepal," International Journal of Civil Engineering, vol. 13, no. 11, pp. 206-224, 2026. Crossref, https://doi.org/10.14445/23488352/IJCE-V13I11P112

Abstract

Road infrastructure plays a significant role for the socio-economic development in Nepal. But this area faces various challenges such as delays, cost overrun, safety issues, quality downfall etc. Unmanaged uncertainties in the technical, financial, environmental, and managerial areas frequently give rise to these problems. The Failure Mode Effect Analysis (FMEA) framework is used in this study to effectively identify, assess, and rank the risk factors affecting Nepal’s road construction project. A total 56 risk factors were identified through an extensive literature review and expert consultations. Data were collected using a structured questionnaire from 90 professionals representing clients, consultants and contractors. Reliability was checked by Cronbach’s alpha, and Validity was checked for extraction values; one factor (G1F1) did not meet the validity threshold of 0.5 and was removed, and only 55 factors were retained and used to test the validity and reliability of the data. A critical risk was ranked by Risk Priority Number (RPN) based on severity, occurrence and detection rating through Relative Important Index (RII). The results show that hazardous working conditions, inaccurate time estimation, extra work due to scope variations, unrealistic project schedule, cost and time overrun, poorly designed project scope and unsuitable construction program planning are the overall risk factors which impact Nepal’s road construction projects. Also, the k-means clustering (k=3) grouped the factors into three tiers: high, moderate and low risk. Spearman’s rank correlation compared the ranking of the three groups. Only unsafe or hazardous working conditions on-site shows (G8F1) is a major risk factor among all stakeholders. The consultant and contractor rankings were moderately correlated, while the client ranking was not significantly correlated with either. The study offers a framework for integrated risk assessment, along with knowledge that can help Nepal’s road infrastructure project plan more proactively, evaluate more effectively and make better decision making.

Keywords

Failure Mode Effect Analysis (FMEA), K-Means clustering, Relative Importance Index (RII), Risk Priority Number (RPN), Road infrastructure project.

References

  1. Project Management Institute, A Guide to the Project Management Body of Knowledge: PMBOK Guide, 4th ed., pp. 1-506, 2008.
    [
    Google Scholar] [Publisher Link]
  2. Mohsen Ahmadi et al., “Comprehensive Risk Management using Fuzzy FMEA and MCDA Techniques in Highway Construction Projects,” Journal of Civil Engineering and Management, vol. 23, no. 2, pp. 300-310, 2017.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  3. Alaa Mohsin Mahdi, and Kadhim Raheim Erzaij, “Developing ANFIS-FMEA Model for Assessment and Prioritization of Potential Trouble Factors in Iraqi Building Projects,” Open Engineering, vol. 14, no. 1, pp. 1-15, 2024.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  4. Usama H. Issa, Khaled Gamal Marouf, and Hamdy Faheem, “Analysis of Risk Factors Affecting the Main Execution Activities of Roadways Construction Projects,” Journal of King Saud University – Engineering Sciences, vol. 35, no. 6, pp. 372-383, 2023. 
    [
    CrossRef] [Google Scholar] [Publisher Link]
  5. Mohamed Sayed Bassiony Ahmed Abd El-Karim, Omar Aly Mosa El Nawawy, and Ahmed Mohamed Abdel-Alim, “Identification and Assessment of Risk Factors Affecting Construction Projects,” HBRC Journal, vol. 13, no. 2, pp. 202-216, 2017.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  6. Mahendra Bhattarai, “Causes of Delay in Construction Projects in Nepal,” Saudi Journal of Engineering and Technology, vol. 8, no. 6, pp. 108-114, 2023.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  7. Thomas A. Carbone, and Donald D. Tippett, “Project Risk Management using the Project Risk FMEA,” Engineering Management Journal, vol. 16, no. 4, pp. 28-35, 2004.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  8. Kamal Sharm, and Dr. M.K Trivedi, “Risk Analysis in Highway Construction Projects using Failure Mode and Effect Analysis,” International Journal for Research in Applied Science & Engineering Technology, vol. 7, no. 6, pp. 311-316, 2019.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  9. Debalina Banerjee Chattapadhyay, Jagadeesh Putta, and Rama Mohan Rao, “Risk Identification, Assessments, and Prediction for Mega Construction Projects: A Risk Prediction Paradigm based on Cross Analytical-Machine Learning Model,” Buildings, vol. 11, no. 4, pp. 1-28, 2021.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  10. Fuad Al-Bataineh, Ahmed Ali Khatatbeh, and Yazan Alzubi, “Unsupervised Machine Learning for Identifying Key Risk Factors Contributing to Construction Delays,” Organization, Technology and Management in Construction, vol. 16, no. 1, pp. 170-185, 2024.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  11. Elanjati Worldailmi, Sinta Wulandari, and Syafa Thania Prawibowo, “A Literature Review: Identification of Risk Factors in Construction Projects,” AIP Conference Proceedings: 3rd Conference on Innovation in Technology and Engineering Science 2022, Padang, Indonesia, vol. 2891, no. 1, 2024. [CrossRef] [Google Scholar] [Publisher Link]
  12. Guiliang Su, and Rana Khallaf, “Research on the Influence of Risk on Construction Project Performance: A Systematic Review,” Sustainability, vol. 14, no. 11, pp. 1-19, 2022.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  13. Saad Alshihri, Khalid Al-Gahtani, and Abdulmohsen Almohsen, “Risk Factors that Lead to Time and Cost Overruns of Building Projects in Saudi Arabia,” Buildings, vol. 12, no. 7, pp. 1-27, 2022.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  14. Amare Tilahun Tessemaa, Getachew Asefa Aleneb, and Natnael Melsew Wolelaw, “Assessment of Risk Factors on Construction Projects in Gondar City, Ethiopia,” Heliyon, vol. 8, no. 11, pp. 1-11, 2022.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  15. Shubham Sharma, and Ashok Kumar Gupta, “Risk Identification and Management in Construction Projects: Literature Review,” International Journal of Humanities, Arts and Social Sciences, vol. 5, no. 6, pp. 224-231, 2019.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  16. Ali Almalki, “Common Risk Factors in Construction Sector – A Review,” International Review of Civil Engineering, vol. 13, no. 6, pp. 455-465, 2022.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  17. Satish Kumar Viswanathan, and Kumar Neeraj Jha, “Critical Risk Factors in International Construction Projects: An Indian Perspective,” Engineering, Construction and Architectural Management, vol. 27, no. 5, pp. 1169-1190, 2020.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  18. Zahra Ghamarimajd et al., “Application of Systems Thinking and System Dynamics in Managing Risks and Stakeholders in Construction Projects: A Systematic Literature Review,” Systems Research and Behavioral Science, vol. 42, no. 6, pp. 1465-1479, 2025.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  19. Erni Farmiza Mohd Zaki et al., “A Systematic Literature Review on Risk Identification towards a Public-Private Partnership Approach in Building Reuse Projects,” International Journal of Property Science, vol. 13, no. 1, pp. 1-20, 2023.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  20. Mukhtar A Kassem, Muhamad Azry Khoiry, and Noraini Hamzah, “Theoretical Review on Critical Risk Factors in Oil and Gas Construction Projects in Yemen,” Engineering, Construction and Architectural Management, vol. 28, no. 4, pp. 934-968, 2021.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  21. Om Prakash Giri, “Assessment of Key Risk Factors Impacting Construction Project Performance,” International Journal of Multidisciplinary Research and Growth Evaluation, vol. 6, no. 1, pp. 1231-1241, 2025.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  22. Soheila Ghafoor et al., “Compliance Risks in the Construction of Residential Buildings: A Systematic Literature Review,” Smart and Sustainable Built Environment, pp. 1-29, 2025.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  23. Saurav Mittal, and Dr. Rajeev Kansal, “Identification of Construction Project Risks in the Indian Context: A Case Study on Building Construction,” International Journal for Research in Applied Science & Engineering Technology, vol. 12, no. 5, pp. 395-402, 2024.
    [
    CrossRef] [Publisher Link]
  24. Daniel Muijs, Doing Quantitative Research in Education with SPSS, SAGE Publications, pp. 1-264, 2010.
    [
    Google Scholar] [Publisher Link]
  25. K. Jayasudha, and Dr. B. Vidivelli, “A Study on Risk Assessment in Construction Projects,” International Journal of Modern Engineering Research (IJMER), vol. 4, no. 9, pp. 20-23, 2014.
    [
    Google Scholar] [Publisher Link]
  26. Shahid Iqbal et al., “Risk Management in Construction Projects,” Technological and Economic Development of Economy, vol. 21, no. 1, pp. 65-78, 2015.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  27. Adel Alshammari, and Farid E. Mohamed Ghazali, “A Comprehensive Review of the Factors and Strategies to Mitigate Construction Projects Delays in Saudi Arabia,” Open Construction & Building Technology Journal, vol. 17, pp. 1-11, 2024.
    [
    CrossRef] [Google Scholar] [Publisher Link]
  28. Abiodun M. Ikotun et al., “K-Means Clustering Algorithms: A Comprehensive Review, Variants Analysis, and Advances in the Era of Big Data,” Information Sciences, vol. 622, pp. 178-210, 2023.
    [
    CrossRef] [Google Scholar] [Publisher Link]